Group Activities by Work Breakdown Structure and Date.
Work breakdown Structure (WBS)
Group activities by WBS Level
Click all or one of the levels (1-9) to display the required WBS levels and activities on the Gantt chart.
Navigate: Select View > WBS > Group activities by WBS level

Note: WBS levels less than the selected WBS are included within that level of WBS upon selection.

Default: The Gantt displays all activities and WBS levels by default